Please enable JavaScript in your browser to use this page.

Beacon Hill area Residents' Parking Zone (RPZ) TRO consultation

Project timeline

The timeline below shows each stage of the proposed RPZ project, including those already completed, the current (active) stage, and future activity should the scheme be approved.

  1. Initial public consultation

    Completed 5 May 2022 to 2 June 2022
  2. Initial public consultation results and decision

    Completed September 2022

    We have published the consultation results and the decision on whether or not this RPZ proposal is to proceed to the next stage.

  3. Traffic Regulation Order (TRO) consultation

    Completed September 2022

    We amended the RPZ proposals, taking into account the feedback we received in the initial consultation.

    We launched a second public consultation, allowing residents to comment on a Traffic Regulation Order (TRO) and the detailed proposals for the RPZ in this area.

  4. Final decision

    Completed December 2022

    Following the feedback we received in the TRO consultation, we have decided not to introduce an RPZ in this area.

    View the consultation feedback report

    View the TRO notice and decision report